Cross Winds Energy Park

Location: Unionville, MI

About the Project

The collection system design involved optimizing the route so as to provide the best possible option for both the client and landowners. The 345kV/34.5kV substation contained four feeders, and it was designed to owner standards. Ulteig also provided civil engineering services including access roads, crane access routes, crane pads, delivery flow plan, intersection improvements, laydown yard, substation side, and yard site design services.

Project Photos


From global energy producers to locally funded cities and private developers to government agencies, the clients we serve encompass a broad range of relationships and projects. Find out why Ulteig is a leader in the engineering industry.