Bluemont Lakes Bike Path

Location: Fargo, ND

About the Project

The Bluemont Lakes Home Owners Association (HOA) in Fargo, N.D., contacted Ulteig to begin looking at options to replace the John Groves Bike Path that wound through their neighboring park.

The improvement project had been on the minds of the Association for quite some time, and in the winter of 2013, the board decided to proceed with the project. The two major goals of the project were to:

  • Improve the drainage in the park
  • Replace the failing bituminous path

The area had been drastically affected by wet weather cycle and the park was no different. The existing pathway was susceptible to moisture due to water pooling on, or adjacent to the path. In addition, when the original path was built, the bituminous pavement was placed directly on topsoil, which is great for growing grass, but not recommended to be under sidewalks, pathways or any other paved surface. Due to the excessive moisture and poor subgrade the pathway was deteriorating, and it was time for a complete reconstruction.

The constructability of the project was a challenge. The park/project is just over .5 miles long, with the only access points at each end, and homes surrounding the park on all sides. In addition, as with all parks, it is home to many beautiful mature trees. With all of these factors considered, low-impact construction methods were required. Skid steers hauled out the existing bike path and transported in gravel. Concrete was brought in by concrete buggies and skid steers making .25 mile trips each way.  These construction methods minimized the amount of disturbance to both the park and the residences adjacent to the park.

The drainage issues were fixed by adding drain tile along the pathway as well as in the existing low areas. Sump pumps will be reinstalled and the storm sewer at the discharge points will be repaired.  Upon completion, the bituminous path with no subgrade will be replaced by a concrete path with a gravel base, and drain tile installation and minor grading will be completed to improve the drainage in the park. During construction, the residents of the HOA stated that they were excited to once again venture along the .5 mile walk through the beautiful, quiet park.